Producing cheaper electricity from solar and pushing electricity price down.

Hillston Solar Project is a 5 Megawatt (MW) solar energy facility with an operating life of 30 years and the option for extensions.
This project will harness clean, renewable solar power to contribute to Australia’s transition to sustainable energy. It aims to deliver long-term environmental benefits, support the local economy, and provide more reliable and affordable electricity for local communities, helping to strengthen the grid and reduce the risk of power outages.
Location

Benefits

Benefit to New South Wales.
- Contributes to the green energy initiatives of the government
- Substantial contributions to a green economy and a sustainable future
- A more stable grid network

Benefit to the local community:
- Creates jobs for the local community
- Utilising local suppliers for accommodation, transport and logistics
- Encourages local economic growth
Project Lifecycle

Step 01:
Planning Stage
- Land Negotiation
- Primary Design

Step 02:
Development Stage
- Land Agreement Signed (16 November 2022)

Step 03:
Application Stage
- Connection Application (April 2023 to June 2025)
- Development Application (approved in December 2024)

Step 04:
Construction & Testing
- Construction & Testing (Feb 2026 to Dec 2026)

Step 05:
Production Stage
- 30 Years